Publicado el 11-10-2018
In the internal and external phases of construction, the roof of the T-2 has a 95% advance, the curtain wall, 98%, escalators
The expansion project of the terminal of the Tocumen International Airport registers a physical advance of 90%, informed the vice president of Engineering and Projects, Mario Caparroso.
In the internal and external phases of construction, the roof of the T-2 has a 95% advance, the curtain wall, 98%, escalators, 95%, floors 75%, roof installation, 95%, structure paint metallic roof, 95%, mobile sidewalks, 98%, concrete walls, 95%, taxiways, 98%, fuel tanks 75% and boarding doors, 90%. For January it is expected that the T-2 has operating about 5 boarding doors temporarily and by the end of June, which is operating in full.
Source: La Estrella
Tweet¡Pardini & Asociados te ofrece la guía Doing Business in Panama 2023! Descargue GRATIS aquí.
Obtenlo ya